Pine Moss Court 4
Here's more photos of the progress on the house at Pine Moss Court, in the order I took them.
 |
Wednesday July 11, 2001, 8:11 PM The tile has been installed in the bathrooms. |
 |
Wednesday July 11, 2001, 8:17 PM New tile in the master bath.
|
 |
Wednesday July 11, 2001, 8:18 PM Wendy's true-blue countertops have been installed in the kitchen. |
 |
Friday July 13, 2001, 3:24 PM Friday the 13th is supposed to be bad luck, but on this Friday, a much-anticipated event occurred: the delivery of the brick. |
 |
Friday July 13, 2001, 3:24 PM We looked very carefully at the brick... it's hard to tell when it's still bound up, but this looks like the right style.
|
 |
Friday July 13, 2001, 3:25 PM The interior electrical work has been finished - all the outlets, switches, and cover plates installed. And I can see it'll take me about a week to go around the house and straighten them all.
|
 |
Friday July 13, 2001, 3:26 PM The forms have been laid for the patio. But they're in the wrong place! We had to call Brighton and tell them not to pour until this was fixed.
|
 |
Saturday July 14, 2001, 8:59 PM On Saturday, we came by to find scaffolds set up, with piles of brick everywhere.
|
 |
Saturday July 14, 2001, 9:01 PM Piles of brick had been set out along the back, leading us to think that the patio wouldn't be poured anytime soon. The forms are still in the wrong place! |
 |
Saturday July 14, 2001, 9:01 PM Piles of brick had been set out on all sides of the house.
|
 |
Monday July 16, 2001, 8:24 PM By Monday, the patio had been poured. Fortunately, Brighton listened to us and moved the forms.
|
 |
Monday July 16, 2001, 8:35 PM At the same time they poured the patio, they also poured the walkway and curbs out front. |
 |
Monday July 16, 2001, 8:36 PM By Monday evening, the brick had been laid along the right side of the house and on the front above the garage.
|
 |
Wednesday July 18, 2001, 6:05 PM By Wednesday, bricking progress had progressed further along the front.
|
 |
Wednesday July 18, 2001, 6:10 PM The bathroom cabinets, which had been delivered unfinished, have now been painted. Some of the bathroom hardware has also been installed.
|
 |
Wednesday July 18, 2001, 6:12 PM Light fixtures and smoke/fire alarms have been installed. The smoke alarms are fitted with red protective covers. |
 |
Wednesday July 18, 2001, 6:12 PM Covers have been installed over all the ventilation openings; this is the return vent near the girls' bedrooms.
|
 |
Friday July 20, 2001, 7:53 PM The brickwork on the front is nearly finished.
|
|